Time & Labour
Concrete Cure Time Calculator
Days to about 70% of strength and the 28-day equivalent at the concrete temperature on site, by the ASTM C1074 maturity method
Updated October 10, 2026 · Live
What this tool does
Scales the published curing period for ordinary Portland, rapid-hardening or slow-hardening cement to the concrete temperature on site using the Arrhenius maturity function of ASTM C1074 with the activation energy NRMCA suggests for Type I cement. Shows the rate of strength gain relative to 20 °C, the days to about 70% of specified strength, the 28-day equivalent, a Nurse-Saul cross-check, the days to frost resistance and a cold- or hot-weather flag, in °C and °F.
Reference curing days divided by the Arrhenius rate of strength gain at the site temperature relative to 20 °C.
People also use
Formula Used
Formula Used
How the concrete cure time calculator works
Concrete gains strength by hydration, and hydration runs faster warm and slower cold, so a curing period written for one temperature has to be stretched or shrunk for another. The way to do that is the maturity method of ASTM C1074, which the National Ready Mixed Concrete Association sets out in CIP 39, Maturity Methods to Estimate Concrete Strength: two placements of the same concrete reach the same strength when they have the same maturity index, and the standard's Arrhenius function converts real age at any temperature into an equivalent age at a reference temperature of 20 °C or 23 °C using an activation energy, for which CIP 39 suggests 42 kJ/mol for Type I portland cement. The calculator uses that function at a 20 °C reference: the rate of strength gain at the site temperature, relative to 20 °C, is exp(−(E ÷ R)(1 ÷ T − 1 ÷ 293.15)) with T in kelvin, and the days to a milestone are the reference days divided by that rate.
The reference days come from the minimum moist-curing periods of ACI Committee 308 as reported in the Federal Highway Administration's curing guide for concrete pavements: 7 days for Type I cement, 14 days for Type II and 3 days for Type III, at curing temperatures of 10 °C or more. Those periods line up with the rule given on Penn State's curing page, that for most structures curing continues for at least 7 days or until 70% of the specified strength, reduced to 3 days for high-early-strength concrete above 10 °C (50 °F). The calculator takes the ACI period for the chosen cement as the time to about 70% at 20 °C, scales it by the Arrhenius rate, and scales 28 days the same way to show when the concrete has had the equivalent of its 28-day reference age.
With the metric default, 15 °C and ordinary Portland cement, the rate is 74% of the rate at 20 °C, so the 7-day reference becomes 9.4 days, the 28-day equivalent 37.8 days, and the 2 days to frost resistance 2.7 days. The US default of 60 °F (15.6 °C) gives 77%, 9.1 days, 36.5 days and 2.6 days. At 5 °C (41 °F) the rate is 39% and the same concrete takes 17.7 days; at 30 °C (86 °F) rapid-hardening cement reaches the mark in 1.7 days.
Two maturity functions
ASTM C1074 allows two functions, and the calculator shows both. The Arrhenius function is the primary result because, as CIP 39 puts it, it "better represents the effect of temperature on strength development". The Nurse-Saul function is the check row: it assumes the rate of strength gain is a straight line in temperature above a datum, and for Type I cement in the 0 to 40 °C range CIP 39 suggests a datum of 0 °C, so the days at the site temperature are the reference days times 20 divided by the temperature in °C. The two agree near 20 °C and part company in the cold: at 5 °C Nurse-Saul gives 28 days where Arrhenius gives 17.7, because a straight line to zero at 0 °C falls faster than the exponential. CIP 39's own illustration, that 7 days at 10 °C "may have the same maturity index" as 3 days at 27 °C, comes out at 70 and 81 °C-days by Nurse-Saul and 3.8 and 4.5 equivalent days by Arrhenius: the same order, not the same number, which is the precision the method offers without a calibrated strength-maturity curve for the actual mix. NRMCA's cold-weather sheet, CIP 27 gives the same physics as a rule of thumb, that a drop of 10 °C (20 °F) roughly doubles the setting time; the Arrhenius rate from 20 °C to 10 °C is 54%, a factor of 1.84.
Cold, hot and freezing
CIP 27 defines cold weather as a period when the average daily temperature is below 5 °C (40 °F) for more than three consecutive days and the air stays at or below 10 °C (50 °F) for more than half of any 24 hours, and the calculator flags any temperature under 5 °C. It also says fresh concrete freezes at about −4 °C (25 °F), that frozen concrete can lose more than half its potential strength, and that concrete "should be protected from freezing until it attains a compressive strength of 500 psi [3.5 MPa], about two days after placement"; the Protect from Freezing row scales those two days by the same rate. CIP 11, Curing In-Place Concrete asks for the placed concrete to be kept above 10 °C (50 °F) and curing to continue for at least 3 to 7 days. At the other end, CIP 12, Hot Weather Concreting warns that concrete cured at high temperatures at an early age "will not be as strong at later ages as the same concrete cured at temperatures in the range of 70 °F (20 °C)", and that high temperature, wind and low humidity drive evaporation and plastic shrinkage; the calculator flags temperatures above 30 °C (86 °F) for that reason, a line drawn for this page since CIP 12 sets no figure, while still showing the faster early gain. The calculator refuses temperatures at or below 0 °C, because at the Nurse-Saul datum there is no strength gain to count and below −4 °C the concrete is freezing, not curing.
What this tool does not do
It is not a strength test. The maturity method proper needs a strength-maturity curve calibrated for the actual mix, as ASTM C1074 describes, and temperature sensors in the pour; this page uses published reference periods and a suggested activation energy for Type I cement, so the result is a planning estimate of time, not a measured strength. It does not model admixtures, supplementary cementitious materials beyond the slow-hardening option, the heat a thick section generates, or the loss of strength when concrete dries out. Formwork striking and loading are decided on strength: Engineers Ireland notes that vertical shutters are typically struck at 16 to 24 hours and slabs at three to seven days, or on a strength requirement, and the temperature-matched cubes or sensors that prove it belong to the engineer.
Adjusting the defaults
Every input is editable. The temperature is the average temperature of the concrete over the curing period, in °C or °F; for a thin slab in the open that is close to the average air temperature, and a thick section runs warmer from its own heat. The cement type picks the reference period: 7 days for ordinary Portland (Type I), 3 days for rapid-hardening (Type III), and 14 days for slow-hardening cements and blends with fly ash or slag, which the FHWA guide reports as the Type II period and as the 10 to 14 days research has suggested for Class F fly ash. The type numbers are ASTM C150 designations; for Canadian cement the same FHWA page lists the equivalents as GU for Type I, MH for Type II and HE for Type III.
On-site considerations
The estimate assumes the concrete stays moist and at the temperature entered for the whole period, which is what curing is. Concrete left to dry in air gains only about half the strength of concrete kept moist, by CIP 11's figure, so the days on this page are days under a curing compound, wet covering or sheeting, not days exposed. In cold weather the temperature that matters is the concrete's, which insulation and retained hydration heat keep above the air temperature; in hot weather it is the concrete's too, which chilled water or ice can bring down by 6 to 12 °C according to CIP 12. Where the schedule turns on an early strength, a sensor and a calibrated curve, or temperature-matched cubes, replace the estimate.
Using this alongside other BuildMetricLab tools
Size the pour with the concrete slab calculator and the concrete footing calculator, set the mix with the concrete mix ratio calculator, and plan the rest of the programme with the excavation time calculator. All BuildMetricLab tools run in your browser with no sign-up, and the formula is on the page so the maths can be checked.
Sources & methodology
Rate of strength gain relative to 20 °C: k = exp(−(E ÷ R)(1 ÷ T − 1 ÷ 293.15 K)), with E = 42,000 J/mol, R = 8.314 J/(mol·K) and T the concrete temperature in kelvin (ASTM C1074 Arrhenius maturity function; activation energy suggested for Type I cement in NRMCA CIP 39). Days to about 70% of specified strength = reference days ÷ k, with reference days 7 (Type I), 3 (Type III) or 14 (Type II or blended) from the ACI 308 minimum moist-curing periods as reported by FHWA and the 7-days-or-70% rule. 28-day equivalent = 28 ÷ k. Protect-from-freezing days = 2 ÷ k (CIP 27: about two days to 3.5 MPa). Nurse-Saul check = reference days × 20 ÷ T(°C), datum 0 °C. US temperatures in °F are converted to °C first. References: NRMCA CIP 39 (maturity functions, 0 °C datum, 42 kJ/mol); FHWA Guide for Curing of Portland Cement Concrete Pavements chapter 4 (ACI 308 periods: Type I 7, Type II 14, Type III 3 days at 10 °C or more); Penn State curing page (7 days or 70%, 3 days for high early strength above 10 °C); NRMCA CIP 27 (cold weather definition, freezing at −4 °C, 3.5 MPa in about two days, 10 °C drop doubles setting time); NRMCA CIP 11 (keep above 10 °C, 3 to 7 days, air-dried concrete about half the strength); NRMCA CIP 12 (hot weather); Engineers Ireland (striking times).
- NRMCA, CIP 39 Maturity Methods to Estimate Concrete Strength: equal maturity gives equal strength; Nurse-Saul temperature-time factor with a 0 °C datum suggested for Type I cement in the 0 to 40 °C range; Arrhenius equivalent age at 20 °C or 23 °C with 42 kJ/mol suggested for Type I cement; the Arrhenius function better represents the effect of temperature
- FHWA, Guide for Curing of Portland Cement Concrete Pavements, chapter 4 (FHWA-RD-02-099): ACI Committee 308 minimum moist-curing periods, Type I 7 days, Type II 14 days, Type III 3 days, assuming curing at 10 °C or more; 10 to 14 days suggested by research for Class F fly ash
- Penn State University, Curing Concrete, Normal, Hot and Cold Weather: curing above 5 °C for at least 7 days or until 70% of the specified strength, 3 days for high-early-strength concrete above 10 °C; air-dried concrete gains only about 50% of the strength of moist-cured
- NRMCA, CIP 27 Cold Weather Concreting: definition of cold weather, fresh concrete freezes at about −4 °C (25 °F), protect until 500 psi (3.5 MPa) at about two days, a 10 °C (20 °F) drop roughly doubles setting time
- NRMCA, CIP 11 Curing In-Place Concrete: keep placed concrete above 50 °F (10 °C), continue curing for at least 3 to 7 days, dry-cured concrete can lose up to 50% of its potential strength
- NRMCA, CIP 12 Hot Weather Concreting: early high-temperature curing lowers later strength relative to curing near 70 °F (20 °C); evaporation and plastic shrinkage; chilled water and ice lower concrete temperature by up to 6 and 12 °C
- ASTM International, ASTM C1074-19e1 Standard Practice for Estimating Concrete Strength by the Maturity Method: temperature-time factor and equivalent age; datum temperature and Q-value guidance
- Engineers Ireland, Assessing concrete strength and the use of temperature matched curing: vertical shutters typically struck at 16 to 24 hours, slabs at three to seven days, or on a strength requirement
Frequently asked questions
Are concrete cure time calculator results accurate enough to order materials?
It is a time estimate, not a materials quantity, so there is nothing to order from it. Its use is scheduling: when a slab has had the equivalent of its 7-day or 28-day reference age at the temperature on site. Each figure comes from a published reference period and the ASTM C1074 Arrhenius function with the activation energy suggested for Type I cement, and the strength actually reached depends on the mix, the moisture and the real concrete temperature. Loading, striking and backfilling decisions are made on measured strength.
Does colder or hotter weather change the cure time?
Yes, that is the whole calculation. The ASTM C1074 maturity method, as set out in NRMCA CIP 39, converts age at one temperature to an equivalent age at 20 °C with an Arrhenius function; at 42 kJ/mol the rate at 10 °C is 54% of the rate at 20 °C and at 30 °C it is 177%, so a 7-day period becomes about 13 days at 10 °C (50 °F) and 4 days at 30 °C (86 °F). NRMCA's cold-weather sheet gives the same effect as a rule of thumb, a 10 °C (20 °F) drop roughly doubling the setting time. Below 5 °C (41 °F) the calculator flags cold-weather practice, and at or below 0 °C (32 °F) it stops, since concrete freezes at about −4 °C (25 °F) and must be protected until it reaches 3.5 MPa (500 psi).
Does this replace professional advice?
No. It is a planning estimate of curing time from the temperature and cement type you enter. When formwork can be struck, when a slab can be loaded and whether cold- or hot-weather measures are needed are engineering decisions made on the specification and on measured strength, under ACI 306R and 305R in the United States and the equivalent guidance elsewhere. For work that affects structure, gas, electrics, plumbing or drainage to a public sewer, use a suitably qualified professional.
How does cement type affect the cure time shown?
The cement type sets the reference period that the temperature then scales. The periods are the ACI Committee 308 minimum moist-curing periods as reported by the Federal Highway Administration: 7 days for Type I, 3 days for Type III (high early strength) and 14 days for Type II, which the calculator also uses for blends with fly ash or slag, where research has suggested 10 to 14 days. Rapid-hardening cement therefore reaches the 70% mark soonest and slow-hardening or blended cement latest at any given temperature.
Spotted something off?