What this tool does
Balances the soil cut from a site against the compacted fill it needs, using bulking and shrinkage factors, and shows the surplus to remove or the shortfall to import.
Calculates adjusted cut and fill volumes using bulking and shrinkage factors to determine earthwork surplus or deficit.
People also use
Formula Used
Formula Used
How the cut and fill calculator works
Cut is soil you dig out. Fill is soil you place and compact to make up levels. The calculator compares the two to show whether the site has soil to spare or needs soil brought in. Dug soil expands and compacted soil is denser, so the two volumes cannot be compared directly. The tool converts everything to in-place (bank) volume first.
The formula is N = C − F ÷ s, where C is the cut in place, F is the fill needed once compacted, and s is the shrinkage factor. A positive N is a surplus to remove. A negative N is the volume to import. The haul-off or import volume in trucks is |N| × the bulking factor.
Typical bulking and shrinkage allowances
Bulking describes how much a volume of soil grows when it is dug. At 1.25, 100 yd³ (76.5 m³) in place becomes 125 yd³ (95.6 m³) loose. Shrinkage describes how much it reduces when compacted. At 0.90, 1 yd³ in place compacts to 0.90 yd³. Real values depend on soil type, moisture and compaction effort, so the defaults are planning values only. Use figures from a geotechnical report or your contractor when you have them.
Worked example, US units: 26 yd³ of cut and 13 yd³ of compacted fill. The fill needs 13 ÷ 0.90 = 14.44 yd³ of in-place soil. The net is 26 − 14.44 = 11.56 yd³ of surplus, which is 11.56 × 1.25 = 14.44 yd³ of loose soil to haul. Worked example, metric: 25 m³ cut and 15 m³ fill gives 25 − 16.67 = 8.33 m³ in place, or 10.42 m³ loose.
The two factors work in opposite directions, which is why a site that looks balanced on paper often is not. Digging 100 yd³ gives 125 yd³ of loose soil, yet it fills only about 90 yd³ of compacted volume. If you place that soil back as compacted fill, you can use less than you dug. Plan a small margin in either direction, and keep any stripped topsoil separate, because it is not fill.
What this tool does not do
It does not work out cut and fill volumes from survey levels, so you need those from your drawings or a survey. It does not allow for topsoil stripping, rock, unsuitable material or the volume of the foundations and drains, and it does not price the haulage. It cannot confirm that the soil on site is suitable to reuse as fill.
On-site considerations for cut and fill
Soil changes volume at each stage, so describe a volume by how it is measured: in place, loose or compacted. Quote lorry loads in loose volume. A deficit of 15 m³ in place needs 18.75 m³ of loose imported soil at a bulking factor of 1.25, and a supplier will quote the load, not the compacted volume.
Find buried services before you dig, using your local utility-locating service. Deep or steep-sided excavations can collapse, and workers need supports or sloped sides. Follow the excavation rules that apply where you are, such as HSE guidance in the UK or OSHA rules in the US.
Codes and compliance
Grading and drainage are regulated locally. Many places require a permit for large earthworks, for changes to site drainage or for work near boundaries, trees or watercourses. Embankments, retaining walls and ground that supports a building need engineered design. Ask your local authority before you start.
Before you order
Ask your contractor which volumes they quote in. Confirm the disposal or import price, which usually depends on the soil type and any testing, and check the number of loads and access for trucks. For imported fill, ask for the specification, because material that compacts differently changes the shrinkage factor and the result.
Adjusting the defaults
Every input is editable. The defaults of 26 yd³ cut, 13 yd³ fill, 1.25 bulking and 0.90 shrinkage are planning values only. A zero for cut or fill is valid, and blank or impossible entries are rejected. Switch between metric and US units at any time and the volumes convert.
If the tool shows a small surplus or deficit, treat it as within the error of the factors. A change in shrinkage from 0.90 to 0.85 moves the fill need from 14.44 to 15.29 yd³, enough to turn a small surplus into a small deficit. Run the numbers with a low and a high factor to see the range.
Using this cut and fill calculator alongside other BuildMetricLab tools
Use the surplus volume with the haul-off, trench and gravel calculators to plan the whole job. All BuildMetricLab tools run in your browser, so nothing you type is sent anywhere, and every formula is shown on the page so you can check the maths.
Sources & methodology
All volumes are balanced as in-situ (bank) volumes. Compacted fill F needs F ÷ s of in-place soil, where s is the shrinkage factor (compacted volume ÷ in-situ volume). Net = cut − F ÷ s. A positive net is surplus to remove; a negative net is the in-situ volume to import. Loosened soil occupies more space, so the haul-off or import volume in trucks is |net| × the bulking factor. With the defaults, 26 yd³ cut and 13 yd³ fill give 26 − 13 ÷ 0.9 = 11.56 yd³ in place, or 14.44 yd³ loose. Some manuals define shrinkage the other way up, so check which convention a figure uses. Cut and fill volumes come from your survey or drawings; the tool does not calculate them from levels, and it ignores topsoil stripping and subsoil replacement.
Frequently asked questions
Are cut and fill calculator results accurate enough to order materials?
They are exact for the volumes and factors you enter, but real soil rarely matches the defaults. Moisture, soil type, compaction effort and how the survey volumes were measured all move the answer, so treat the result as a planning figure and confirm haul-off and import quantities with your earthworks contractor.
What bulking and shrinkage factors should I use?
The defaults are a bulking factor of 1.25 and a shrinkage factor of 0.90, which are general-purpose planning values. Bulking is how much a volume of soil grows when dug. Shrinkage is how much it reduces once compacted: 0.90 means 1.00 m³ of in-place soil compacts to 0.90 m³. Both depend on soil type, moisture and compaction, so use figures from a geotechnical report or your contractor where you can.
Does this tool replace a licensed contractor or engineer?
No. This is a planning estimator only. Grading, drainage and any work that affects structure, slopes or building code needs a licensed contractor or engineer, and excavations need a safe working method and a check for buried services.
Can I adjust the bulking and shrinkage factors?
Yes, both are editable. The bulking factor sizes the volume of loosened soil a truck has to carry: the surplus in place multiplied by it. The shrinkage factor sizes how much in-place soil is needed to make the compacted fill: fill volume divided by it. Typical bulking factors run from about 1.10 to 1.40 and shrinkage factors from about 0.80 to 0.95 depending on soil, so check your report or supplier.
Spotted something off?